and a copy of this plan must be provided to FEMA by the owner of the levee system when recognition is being sought or when the plan for a previously recognized system is revised in any manner. All maintenance activities must be under the jurisdiction of a Federal or State agency, an agency created by Federal or State law, or an agency of a community participating in the NFIP that must assume ultimate responsibility for maintenance. This plan must document the formal procedure that ensures that the stability, height, and overall integrity of the levee and its associated structures and systems are maintained. At a minimum, maintenance plans shall specify the maintenance activities to be performed, the frequency of their performance, and the person by name or title responsible for their performance.

(e) Certification requirements. Data submitted to support that a given levee system complies with the structural requirements set forth in paragraphs (b)(1) through (7) of this section must be certified by a registered professional engineer. Also, certified as-built plans of the levee must be submitted. Certifications are subject to the definition given at §65.2 of this subchapter. In lieu of these structural requirements, a Federal agency with responsibility for levee design may certify that the levee has been adequately designed and constructed to provide protection against the base flood.

[51 FR 30316, Aug. 25, 1986]

§ 65.11 Evaluation of sand dunes in mapping coastal flood hazard areas. (a) General conditions. For purposes of the NFIP, FEMA will consider storminduced dune erosion potential in its determination of coastal flood hazards and risk mapping efforts. The criterion to be used in the evaluation of dune erosion will apply to primary frontal dunes as defined in §59.1, but does not apply to artificially designed and constructed dunes that are not well-established with long-standing vegetative cover, such as the placement of sand materials in a dune-like formation.

(b) Evaluation criterion. Primary frontal dunes will not be considered as effective barriers to base flood storm surges and associated wave action

where the cross-sectional area of the primary frontal dune, as measured perpendicular to the shoreline and above the 100-year stillwater flood elevation and seaward of the dune crest, is equal to, or less than, 540 square feet.

(c) Exceptions. Exceptions to the evaluation criterion may be granted where it can be demonstrated through authoritative historical documentation that the primary frontal dunes at a specific site withstood previous base flood storm surges and associated wave action.

[53 FR 16279, May 6, 1988]

§ 65.12 Revision of flood insurance rate maps to reflect base flood elevations caused by proposed encroachments.

(a) When a community proposes to permit encroachments upon the flood plain when a regulatory floodway has not been adopted or to permit encroachments upon an adopted regulatory floodway which will cause base flood elevation increases in excess of those permitted under paragraphs (c)(10) or (d)(3) of §60.3 of this subchapter, the community shall apply to the Administrator for conditional approval of such action prior to permitting the encroachments to occur and shall submit the following as part of its application:

(1) A request for conditional approval of map change and the appropriate initial fee as specified by § 72.3 of this subchapter or a request for exemption from fees as specified by §72.5 of this subchapter, whichever is appropriate;

(2) An evaluation of alternatives which would not result in a base flood elevation increase above that permitted under paragraphs (c)(10) or (d)(3) of §60.3 of this subchapter demonstrating why these alternatives are not feasible;

(3) Documentation of individual legal notice to all impacted property owners within and outside of the community, explaining the impact of the proposed action on their property.

(4) Concurrence of the Chief Executive Officer of any other communities impacted by the proposed actions;

(5) Certification that no structures are located in areas which would be impacted by the increased base flood elevation;

(6) A request for revision of base flood elevation determination according to the provisions of §65.6 of this part;

(7) A request for floodway revision in accordance with the provisions of § 65.7 of this part;

(b) Upon receipt of the Administrator's conditional approval of map change and prior to approving the proposed encroachments, a community shall provide evidence to the Administrator of the adoption of flood plain management ordinances incorporating the increased base flood elevations and/ or revised floodway reflecting the postproject condition.

(c) Upon completion of the proposed encroachments, a community shall provide as-built certifications in accordance with the provisions of § 65.3 of this part. The Administrator will initiate a final map revision upon receipt of such certifications in accordance with part 67 of this subchapter.

[53 FR 16279, May 6, 1988]

§ 65.13 Mapping and map revisions for areas subject to alluvial fan flooding.

This section describes the procedures to be followed and the types of information FEMA needs to recognize on a NFIP map that a structural flood control measure provides protection from the base flood in an area subject to alluvial fan flooding. This information must be supplied to FEMA by the community or other party seeking recognition of such a flood control measure at the time a flood risk study or restudy is conducted, when a map revision under the provisions of part 65 of this subchapter is sought, and upon request by the Administrator during the review of previously recognized flood control measures. The FEMA review will be for the sole purpose of establishing appropriate risk zone determinations for NFIP maps and shall not constitute a determination by FEMA as to how the flood control measure will perform in a flood event.

(a) The applicable provisions of §§ 65.2, 65.3, 65.4, 65.6, 65.8 and 65.10 shall

also apply to FIRM revisions involving alluvial fan flooding.

(b) The provisions of §65.5 regarding map revisions based on fill and the provisions of part 70 of this chapter shall not apply to FIRM revisions involving alluvial fan flooding. In general, elevations of a parcel of land or a structure by fill or other means, will not serve as a basis for removing areas subject to alluvial fan flooding from an area of special food hazards.

(c) FEMA will credit on NFIP maps only major structural flood control measures whose design and construction are supported by sound engineering analyses which demonstrate that the measures will effectively eliminate alluvial fan flood hazards from the area protected by such measures. The provided analyses must include, but are not necessarily limited to, the following:

(1) Engineering analyses that quantify the discharges and volumes of water, debris, and sediment movement associated with the flood that has a one-percent probability of being exceeded in any year at the apex under current watershed conditions and under potential adverse conditions (e.g., deforestation of the watershed by fire). The potential for debris flow and sediment movement must be assessed using an engineering method acceptable to FEMA. The assessment should consider the characteristics and availability of sediment in the drainage basin above the apex and on the alluvial fan.

(2) Engineering analyses showing that the measures will accommodate the estimated peak discharges and volumes of water, debris, and sediment, as determined in accordance with paragraph (c)(1) of this section, and will withstand the associated hydrodynamic and hydrostatic forces.

(3) Engineering analyses showing that the measures have been designed to withstand the potential erosion and scour associated with estimated discharges.

(4) Engineering analyses or evidence showing that the measures will provide protection from hazards associated with the possible relocation of flow paths from other parts of the fan.

(5) Engineering analyses that assess the effect of the project on flood hazards, including depth and velocity of floodwaters and scour and sediment deposition, on other areas of the fan.

(6) Engineering analyses demonstrating that flooding from scources other than the fan apex, including local runoff, is either insignificant or has been accounted for in the design.

(d) Coordination. FEMA will recognize measures that are adequately designed and constructed, provided that: evidence is submitted to show that the impact of the measures on flood hazards in all areas of the fan (including those not protected by the flood control measures), and the design and maintenance requirements of the measures, were reviewed and approved by the impacted communities, and also by State and local agencies that have jurisdiction over flood control activities.

(e) Operation and maintenance plans and criteria. The requirements for operation and maintenance of flood control measures on areas subject to alluvial fan flooding shall be those specified under §65.10, paragraphs (c) and (d), when applicable.

(f) Certification requirements. Data submitted to support that a given flood control measure complies with the requirements set forth in paragraphs (c) (1) through (6) of this section must be certified by a registered professional engineer. Also, certified as-built plans of the flood control measures must be submitted. Certifications are subject to the definition given at § 65.2.

(Approved by the Office of Management and Budget under control number 3067-0147.)

[54 FR 33551, Aug. 15, 1989]

§ 65.14 Remapping of areas for which local flood protection systems no longer provide 100-year flood protection.

(a) General. (1) This section describes the procedures to follow and the types of information FEMA requires to designate flood control restoration zones. A community may be eligible to apply for this zone designation if the Director determines that it is engaged in the process of restoring a flood protection system that was:

(i) Constructed using Federal funds;

(ii) Recognized as providing 100-year flood protection on the community's effective Flood Insurance Rate Map; and

(iii) Decertified by a Federal agency responsible for flood protection design or construction.

(2) Where the Director determines that a community is in the process of restoring its flood protection system to provide 100-year minimum flood protection, a Flood Insurance Rate Map will be prepared that designates the temporary flood hazard areas as a flood control restoration zone (Zone AR). Existing Special Flood Hazard Areas shown on the community's effective Flood Insurance Rate Map that are further inundated by Zone AR flooding shall be designated as a "dual" flood insurance rate zone, Zone AR/AE or AR/AH with Zone AR base flood elevations, and AE or AH with base flood elevations and Zone AR/AO with Zone AR base flood elevations and Zone AO with flood depths, or Zone AR/A with Zone AR base flood elevations and Zone A without base flood elevations.

(b) Limitations. A community may have a flood control restoration zone designation only once for the purposes of restoring a given flood protection system and must complete restoration of the system or meet the requirements of 44 CFR 61.12 within a specified period, not to exceed ten (10) years from the date of submittal of the community's application for designation of a flood control restoration zone. The community may not extend this period. The information specified in this section must be supplied to FEMA by the community as part of its request for designation of a flood control restoration zone.

(c) Exclusions. The provisions of these regulations do not apply in a coastal high hazard area as defined in 44 CFR 59.1, including areas that would be subject to coastal high hazards as a result of the decertification of a flood protection system shown on the community's effective Flood Insurance Rate Map (FIRM) as providing 100-year protection.

(d) Effective date for risk premium rates. The effective date for any risk premium rates established for Zone AR

shall be the effective date of the revised Flood Insurance Rate Map showing AR Zone designations.

(e) Application and submittal requirements for designation of a flood control restoration zone. A community must submit a written request to the Director, signed by the community's Chief Executive Officer, for a flood plain designation as a flood control restoration zone. The request must include a legislative action by the community requesting the designation. The Director will not initiate any action to designate flood control restoration zones without receipt of the formal request from the community that complies with all requirements of this section. The Director reserves the right to request additional information from the community to support or further document the community's formal request for designation of a flood control restoration zone, if deemed necessary. At a minimum, each request must include the following:

(1) A statement whether, to the best of the knowledge of the community's Chief Executive Officer, the flood protection system is currently the subject matter of litigation before any Federal, State or local court or administrative agency, and if so, the purpose of that litigation;

(2) A statement whether the community has previously requested a determination with respect to the same subject matter from the Director, and if so, a statement that details the disposition of such previous request;

(3) A statement from the community and certification by a Federal agency responsible for flood protection design or construction that the existing flood control system shown on the effective Flood Insurance Rate Map was built using Federal funds, that it no longer provides 100-year flood protection, but that it continues to provide at least a 35-year level of protection;

(4) A statement identifying the local project sponsor responsible for restoration of the flood protection system to the 100-year or greater level of flood protection;

(5) a copy of a study, performed by a Federal agency responsible for flood protection design or construction in consultation with the local project

sponsor, which demonstrates a Federal interest in restoration of the system and which deems that the flood protection system is restorable to a 100-year or greater level of flood protection.

(6) A joint statement from the Federal agency responsible for flood protection design or construction involved in restoration of the flood protection system and the local project sponsor certifying that the design and construction of the flood control system involves Federal funds, and that the restoration of the flood protection system will provide 100-year or greater flood protection;

(7) A restoration plan to return the system to a 100-year or greater level of protection. At a minimum, this plan must:

(i) List all important project elements, such as acquisition of permits, approvals, and contracts and construction schedules of planned features;

(ii) Identify anticipated start and completion dates for each element, as well as significant milestones and dates;

(iii) Identify the date on which "as built" drawings and certification for the completed restoration project will be submitted. This date must provide for a restoration period not to exceed, ten (10) years from the date of submittal of the community's application for designation as a flood control restoration zone, or;

(iv) Identify the date on which the community will submit a request for a finding of adequate progress that meets all requirements of §61.12. This date may not exceed ten (10) years from the date of submittal of the community's application for designation as a flood control restoration zone;

(8) An official map of the community or legal description, with supporting documentation, that the community will adopt as part of its floodplain management measures, which designates developed areas as defined in § 59.1 and as further defined in §60.3(f). (f) Review and response by the Director. The review and response by the Director shall be in accordance with procedures specified in §65.9.

(g) Requirements for maintaining designation of a flood control restoration zone. During the restoration period, the

community and the cost-sharing Federal agency must certify annually to the FEMA Regional Office having jurisdiction that the restoration will be completed in accordance with the restoration plan within the time period specified by the plan. In addition, the community and the Federal agency will update the restoration plan and will identify any permitting or construction problems that will delay the project completion from the restoration plan previously submitted to the Director. The FEMA Regional Office having jurisdiction will make an annual assessment and recommendation to the Director as to the viability of the restoration plan and will conduct periodic on-site inspections of the flood protection system under restoration.

(h) Procedures for removing flood control restoration zone designation due to adequate progress or complete restoration of the flood protection system. At any time during the restoration period, the community may provide written evidence of certification from a Federal agency having flood protection design or construction responsibility that the necessary improvements have been completed and that the system has been restored to provide a minimum 100-year level of protection, or may submit a request for a finding of adequate progress that meets all requirements of section 61.12. If the Director determines that adequate progress has been made, FEMA will revise the zone designation from a flood control restoration zone designation to Zone A99. After the improvements have been completed and certified by a Federal agency as providing a minimum 100year level of protection, FEMA will revise the Flood Insurance Rate Map to reflect the completed flood control system.

(i) Procedures for removing flood control restoration zone designation due to non-compliance with the restoration schedule or as a result of a finding that satisfactory progress is not being made to complete the restoration. At any time during the restoration period, should the Director determine that the restoration will not be completed in accordance with the time frame specified in the restoration plan, or that satisfactory progress is not being made to

restore the flood protection system to provide complete flood protection in accordance with the restoration plan, the Director shall notify the community and the responsible Federal agency, in writing, of the determination, the reasons for that determination, and that the Flood Insurance Rate Map will be revised to remove the flood control restoration zone designation. Within thirty (30) days of such notice, the community may submit written information that provides assurance that the restoration will be completed in accordance with the time frame specified in the restoration plan, or that satisfactory progress is being made to restore complete protection in accordance with the restoration plan, or that, with reasonable certainty, the restoration will be completed within the maximum restoration period, which may not exceed ten (10) years from the date of submittal of the community's application for designation of a flood control restoration zone. On the basis of this information the Director may suspend the decision to revise the Flood Insurance Rate Map to remove the flood control restoration zone designation. If the community does not submit any information, or if, based on a review of the information submitted, there is sufficient cause to find that the restoration will not be completed as provided for in the restoration plan, the Director shall revise the Flood Insurance Rate Map, in accordance with 44 CFR Part 67, and shall remove the flood control restoration zone designations and shall redesignate those areas as Zone A1-30, AE, AH, AO, or A.

[59 FR 53599, Oct. 25, 1994]

§ 65.15 List of communities submitting new technical data.

This section provides a cumulative list of communities where modifications of the base flood elevation determinations have been made because of submission of new scientific or technical data. Due to the need for expediting the modifications, the revised map is already in effect and the appeal period commences on or about the effective date of the modified map. An interim rule, followed by a final rule, will list the revised map effective date,

« AnteriorContinuar »