Advisory Committee on Reactor Safety Atomic Safety Licensing Board Panel Atomic Safety Licensing Appeal Board Pre JAN 20, 1977 Commission OMB Estimate to OMB Approved Ceiling $ 100 $ 100 1,600 1,600 $ 100 1,600 20 20 20 100 100 100 OMB Approved Ceiling QUESTION 4. Please provide tables showing: (a) The number and location of nuclear power facilities licensed to operate in the United States as of April 1, 1977 and indicate the date commercial operation began for each such facility. Also, show the expected life of each such facility and the energy produced daily (in kwh). 1/ Based on total net electrical energy generated during 1976. Full term licenses are issued for a 40 year period from issuance of the construction permit. The eight plants identified above (*) currently operating under provisional operating licenses have applied for full-term licenses. Source: NUREG 0020 Operating Units Status Report |