(2) The Administrator shall enter into arrangements, wherever practicable and desirable, to provide monitoring of full-scale solid waste facilities (whether or not constructed or operated under this Act) for purposes of obtaining information concerning the performance, and other aspects, of such facilities. Where the Administrator provides only monitoring and evaluation instruments or personnel (or both) or funds for such instruments or personnel and provides no other financial assistance to a facility, notwithstanding section 8001 (c) (3), title to any invention made or conceived of in the course of developing, constructing, or operating such facility shall not be required to vest in the United States and patents respecting such invention shall not be required to be issued to the United States.

(d) PROHIBITION.-After the date of enactment of this section, the Administrator shall not construct or operate any full-scale facility (except by contract with public agencies or authorities or private persons).

SPECIAL STUDY AND DEMONSTRATION PROJECTS ON

RECOVERY OF USEFUL ENERGY AND MATERIALS

SEC. 8005. (a) STUDIES.-The Administrator shall con- 42 U.S.C. 6985 duct studies and develop recommendations for administrative or legislative action on

(1) means of recovering materials and energy from solid waste, recommended uses of such materials and energy for national or international welfare, including identification of potential markets for such recovered resources, the impact of distribution of such resources on existing markets, and potentials for energy conservation through resource conservation and resource recovery;

(2) actions to reduce waste generation which have been taken voluntarily or in response to governmental action, and those which practically could be taken in the future, and the economic, social, and environmental consequences of such actions;

(3) methods of collection, separation, and containerization which will encourage efficient utilization of facilities and contribute to more effective programs of reduction, reuse, or disposal of wastes;

(4) the use of Federal procurement to develop market demand for recovered resources;

(5) recommended incentives (including Federal grants, loans, and other assistance) and disincentives to accelerate the reclamation or recycling of materials from solid wastes, with special emphasis on motor vehicle hulks;

(6) the effect of existing public policies, including subsidies and economic incentives and disincentives, percentage depletion allowances, capital gains treat

42 U.S.C. 6986

ment and other tax incentives and disincentives, upon the recyling and reuse of materials, and the likely effect of the modification or elimination of such incentives and disincentives upon the reuse, recycling and conservation of such materials;

(7) the necessity and method of imposing disposal or other charges on packaging, containers, vehicles, and other manufactured goods, which charges would reflect the cost of final disposal, the value of recoverable components of the item, and any social costs associated with nonrecycling or uncontrolled disposal of such items; and

(8) the legal constraints and institutional barriers to the acquisition of land needed for solid waste management, including land for facilities and disposal sites;

(9) in consultation with the Secretary of Agriculture, agricultural waste management problems and practices, the extent of reuse and recovery of resources in such wastes, the prospects for improvement, Federal, State, and local regulations governing such practices, and the economic, social, and environmental consequences of such practices; and

(10) in consultation with the Secretary of the Interior, mining waste management problems, and practices, including an assessment of existing authorities, technologies, and economics, and the environmental and public health consequences of such practices.

(b) DEMONSTRATION.-The Administrator is also authorized to carry out demonstration projects to test and demonstrate methods and techniques developed pursuant to subsection (a).

(c) APPLICATION OF OTHER SECTION.-Section 8001 (b) and (c) shall be applicable to investigations, studies, and projects carried out under this section.

GRANTS FOR RESOURCE RECOVERY SYSTEMS AND IMPROVED
SOLID WASTE DISPOSAL FACILITIES

SEC. 8006. (a) AUTHORITY.-The Administrator is authorized to make grants pursuant to this section to any State, municipal, or interstate or intermunicipal agency for the demonstration of resource recovery systems or for the construction of new or improved solid waste disposal facilities.

(b) CONDITIONS.-(1) Any grant under this section for the demonstration of a resource recovery system may be made only if it (A) is consistent with any plans which meet the requirements of subtitle D of this Act; (B) is consistent with the guidelines recommended pursuant to section 1008 of this Act; (C) is designed to

provide areawide resource recovery systems consistent with the purposes of this Act, as determined by the Administrator, pursuant to regulations promulgated under subsection (a) of this section; and (D) provides an equitable system for distributing the costs associated with contruction, operation, and maintenance of any resource recovery system among the users of such system. (2) The Federal share for any project to which paragraph (1) applies shall not be more than 75 percent. (c) LIMITATIONS.-(1) A grant under this section for the construction of a new or improved solid waste disposal facility may be made only if—

(A) a State or interstate plan for solid waste disposal has been adopted which applies to the area involved, and the facility to be constructed (i) is consistent with such plan, (ii) is included in a comprehensive plan for the area involved which is satisfactory to the Administrator for the purposes of this Act, and (iii) is consistent with the guidelines recommended under section 1008, and

(B) the project advances the state of the art by applying new and improved techniques in reducing the environmental impact of solid waste disposal, in achieving recovery of energy or resources, or in recycling useful materials.

(2) The Federal share for any project to which paragraph (1) applies shall be not more than 50 percent in the case of a project serving an area which includes only one municipality, and not more than 75 percent in any other case.

(d) REGULATIONS.-(1) The Administrator shall promulgate regulations establishing a procedure for awarding grants under this section which

(A) provides that projects will be carried out in communities of varying sizes, under such conditions as will assist in solving the community waste pròblems of urban-industrial centers, metropolitan regions, and rural areas, under representative geographic and environmental conditions; and

(B) provides deadlines for submission of, and action on, grant requests.

(2) In taking action on applications for grants under this section, consideration shall be given by the Administrator (A) to the public benefits to be derived by the construction and the propriety of Federal aid in making such grant; (B) to the extent applicable, to the economic and commercial viability of the project (including contractual arrangements with the private sector to market any resources recovered; (C) to the potential of such project for general application to community solid waste disposal problems; and (D) to the use by the applicant of comprehensive regional or metropolitan area planning.

42 U.S.C. 6987

(e) ADDITIONAL LIMITATIONS.-A grant under this section

(1) may be made only in the amount of the Federal share of (A) the estimated total design and construction costs, plus (B) in the case of a grant to which subsection (b) (1) applies, the first-year operation and maintenance costs;

(2) may not be provided for land acquisition or (except as otherwise otherwise provided in paragraph (1) (B)) for operating or maintenance costs;

(3) may not be made until the applicant has made provision satisfactory to the Administrator for proper and efficient operation and maintenance of the project (subject to paragraph (1)(B)); and

(4) may be made subject to such conditions and requirements, in addition to those provided in this section, as the Administrator may require to properly carry out his functions pursuant to this Act. For purposes of paragraph (1), the non-Federal share may be in any form, including, but not limited to, lands or interests therein needed for the project or personal property or services, the value of which shall be determined by the Administrator.

(f) SINGLE STATE. (1) Not more than 15 percent of the total of funds authorized to be appropriated for any fiscal year to carry out this section shall be granted under this section for projects in any one State.

(2) The Administrator shall prescribe by regulation the manner in which this subsection shall apply to a grant under this section for a project in an area which includes all or part of more than one State.

AUTHORIZATION OF APPROPRIATIONS

SEC. 8007. There are authorized to be appropriated not to exceed $35,000,000 for the fiscal year 1978 to carry out the purposes of this subtitle (except for section 8002).

TOXIC SUBSTANCES CONTROL ACT

[blocks in formation]