(1) Records subject to the provisions of 5 U.S.C. 552(b)(1) as classified material;

(2) Investigatory material compiled for law enforcement purposes [except to the extent that the system is more broadly exempt under 5 U.S.C. 552a(j)(2) covering records maintained by an agency whose principal function pertains to the enforcement of criminal laws] provided, however, that is such record is used as a basis for denying an individual any right, privilege, or benefit to which the individual would be entitled in the absence of that record, the individual must be granted access to that record except to the extent that access would reveal the identity of a confidential source who furnished the information to the Government under an express promise that his identity would be held in confidence, or, prior to September 27, 1975, under an implied promise that his identity would be held in confidence;

(3) Records maintained to provide protective services to the President of the United States or other individuals pursuant to 18 U.S.C. 3056;

(4) Records required by statute to be maintained and used solely as statistical records;

(5) Investigatory material compiled solely for determining suitability, eligibility, or qualifications for Federal civilian employment, military service, Federal contracts, or access to classified information, but only to the extent that disclosure of such material would reveal the identity of a source who furnished information to the Government under an express promise that his identity would be held in confidence, or, prior to September 27, 1975, under an implied promise that his identity would be held in confidence;

(6) Testing or examination material used solely to determine individual qualifications for appointment or promotion in the Federal service the disclosure of which would compromise the objectivity or fairness of the testing or examination process; or

(7) Material used to evaluate potential for promotion in the armed services, but only to the extent that the disclosure of such material would reveal the identity of a source who furnished the information to the Govern

ment under an express promise that his identity would be held in confidence, or, prior to September 27, 1975, under an implied promise that his identity would be held in confidence;

(b) Publication in the FEDERAL REGISTER is made in accordance with the requirements (including general public notice) of the Administrative Procedure Act, 5 U.S.C. 553, to include, at a minimum:

(1) The name of the system of records;

(2) The specific provision or provisions of the Privacy Act of 1974, and the appropriate sections of this part promulgated pursuant thereto, from which the system is to be exempted; and

(3) The reasons for the exemption; and

(c) The system of records is exempted from one or more of the following provisions of the Privacy Act and the appropriate sections of this part promulgated pursuant thereto:

(1) 5 U.S.C. 552a(c)(3); 18 18 CFR 3b.226(c)-Making the accounting of disclosures available to the individual named in the record at his request;

(2) 5 U.S.C. 552a(d); 18 CFR 3b.221, 3b.224 Granting an individual the right of access to his records and permitting him to request amendment of such;

(3) 5 U.S.C. 552a(e)(1); 18 CFR 3b.201(a)—Requiring maintenance of relevant and necessary information in a system of records as required by statute or Executive order of the President;

(4) 5 U.S.C. 552a(e)(4)(G); 18 CFR 3b.3(a)(8)-Requiring a description of procedures for determining if a system contains a record on an individual in the public notice of the system of records;

(5) 5 U.S.C. 552a(e)(4)(H); 18 CFR 3b.3(a)(9)—Requiring a description of procedures for gaining access to and contesting the contents of a record in the public notice of the system of records;

(6) 5 U.S.C. 552a(e)(4)(I); 18 CFR 3b.3(a)(10)—Requiring a description of the categories of the sources of records in the public notice of the system of records; and

[blocks in formation]

divulging any fact or information which may come to his or her knowledge during the course of examination of books or other accounts.

(b) The nature and time of any proposed action by the Commission are confidential and shall not be divulged to anyone outside the Commission. The Secretary of the Commission has the exclusive responsibility and authority for authorizing the initial public release of information concerning Commission proceedings.

§3c.3 Reporting fraud, waste, abuse, and corruption and cooperation with official inquiries.

(a) Employees shall, in fulfilling the obligation of 5 CFR 2635.101(b)(11), report fraud, waste, abuse, and corruption in Commission programs, including on the part of Commission employees, contractors, subcontractors, grantees, or other recipients of Commission financial assistance, to the Office of Inspector General or other appropriate Federal authority.

(b) All alleged violations of the ethical restrictions described in §3c.1 that are reported in accordance with paragraph (a) of this section to an appropriate authority within the Commission shall in turn be referred by that authority to the Designated Agency Ethics Official or his or her designee, or the Inspector General.

(c) Employees shall cooperate with official inquiries by the Inspector General; they shall respond to questions truthfully under oath when required, whether orally or in writing, and must provide documents and other materials concerning matters of official interest. An employee is not required to respond to such official inquiries if answers or testimony may subject the employee to criminal prosecution.

SUBCHAPTER B-REGULATIONS UNDER THE FEDERAL POWER

ACT

PART 4-LICENSES, PERMITS, EX- Subpart E-Application for License for EMPTIONS, AND DETERMINATION

[blocks in formation]

Major

Unconstructed Project and

Major Modified Project

[blocks in formation]

4.30 Applicability and definitions.

[blocks in formation]

4.31 Initial or competing application: who may file.

[blocks in formation]

4.93

Action on exemption applications.

[blocks in formation]
[blocks in formation]

§ 4.1 Initial cost statement.

(a) Notification of Commission. When a project is constructed under a license issued under the Federal Power Act, the licensee shall, within one one year after the original project is ready for service, file with the Commission a letter, in quadruplicate, declaring that the original costs have been booked in compliance with the Commission's Uniform System of Accounts and the books of accounts are ready for audit. (b) Licensee's books. The licensee's books of accounts for each project shall be maintained in such a fashion that each year's additions, betterments, and delections to the project may be readily ascertained.

(c) Availability of information to the public. The information made available to the Commission in accordance with this section must be available to the public for inspection and copying when specifically requested.

(d) Compliance with the Act. Compliance with the provisions of this section satisfies the filing requirements of section 4(b) of the Federal Power Act (16 U.S.C. 797(b)).

[Order 53, 44 FR 61948, Oct. 29, 1979]

§4.3 Report on project cost.

(a) Scheduling an audit. When the original cost declaration letter, filed in accordance with §4.1 is received by the Commission, its representative will sechedule and conduct an audit of the books, cost records, engineering reports, and other records supporting the project's original cost. The audit may include an inspection of the project works.

(b) Project records. The cost records shall be supported by memorandum accounts reflecting the indirect and overhead costs prior to their spread to primary accounts as well as all the details of allocations including formulas utilized to spread the indirect and overhead costs to primary accounts.

(c) Report by Commission staff. Upon completion of the audit, a report will be prepared for the Commission setting forth the audit findings and recommendations with respect to the cost as claimed.

[Order 53, 44 FR 61948, Oct. 29, 1979]

§4.4 Service of report.

Copies of such report will be served by certified mail upon said licensees, and copies will also be sent to the State public service commission, or if the States has not regulatory agency, to the Governor of the State where such project is located, and to such other parties as the Commission shall prescribe, and the report will be made available for public inspection at the time of service upon the licensee.

(Administrative Procedure Act, 5 U.S.C. 551– 557 (1976); Federal Power Act, as amended, 16 U.S.C. 291-628 (1976 & Supp. V 1981), Dept. of Energy Organization Act 42 U.S.C. 7101-7352 (Supp. V 1981); E.O. 12009, 3 CFR 142 (1978))

[Order 141, 12 FR 8485, Dec. 19, 1947, as amended by Order 344, 48 FR 49010, Oct. 24, 1983]

§4.5 Time for filing protest.

Thirty days after service thereof will be allowed to such licensee within which to file a protest to such reports. If no protest is filed within the time allowed, the Commission will issue such

order as may be appropriate. If a protest is filed, a public hearing will be ordered in accordance with subpart E of part 385 of this chapter.

[Order 141, 12 FR 8485, Dec. 19, 1947, as amended by Order 225, 47 FR 19056, May 3, 1982]

§ 4.6 Burden of proof.

The burden of proof to sustain each item of claimed cost shall be upon the licensee and only such items as are in the opinion of the Commission supported by satisfactory proof may be entered in the electric plant accounts of the licensee.

[Order 53, 44 FR 61948, Oct. 29, 1979]

§4.7 Findings.

(a) Commission determination. Final action by the Commission will be in the form of an order served upon all parties to the proceeding. One copy of the order will be furnished to the Secretary of Treasury by the Commission.

(b) Adjustments to licensee's books. The licensee's books of account for the project shall be adjusted to conform to the actual legitimate cost as revised by the order of the Commission. These adjustments and the project may be audited by Commission representatives, as scheduled.

[Order 53, 44 FR 61948, Oct. 29, 1979]

Subpart B-Determination of Fair

Value of Constructed Projects,
Under Section 23(a) of the Act

§4.10 Valuation data.

(a) Notification of Commission. In every case arising under section 23(a) of the Federal Power Act that requires the determination of the fair value of a project already constructed, the licensee shall, within six months after the date of issuance of a license, file with the Commission a letter, in quadruplicate.

(b) Contents of letter. The letter referred to in paragraph (a) shall contain a statement to the effect that an inventory and appraisal in detail, as of the effective date of the license, of all property subject thereto and to be so valued has been completed. The letter shall also include a statement to the

effect that the actual legitimate original cost, or if not known, the estimated original cost, and accrued depreciation of the property, classified by prime accounts as prescribed in the Commission's Uniform System of Accounts, have been established.

(c) Licensee's books. The licensee's books of account for each project shall be maintained in such a fashion that each year's additions, betterments, and deletions to the projects may be readily ascertained.

(d) Availability of information to the public. The information made available to the Commission in accordance with this section must be available for inspection and copying by the public when specifically requested.

[Order 53, 44 FR 61948, Oct. 29, 1979]

§4.11 Reports.

Representatives of the Commission will inspect the project works, engineering reports, and other records of the project, check the inventory and make an appraisal of the property and an audit of the books, records, and accounts of the licensee relating to the property to be valued, and will prepare a report of their findings with respect to the inventory, appraisal, original cost, accrued depreciation, and fair value of the property.

§ 4.12 Service of report.

A copy of such report will be served by certified mail upon said licensee, and copies will also be sent to the State public service commission, or if the State has no regulatory agency, to the Governor of the State where such project is located. The report will be made available for public inspection at the time of service upon the licensee. (Administrative Procedure Act, 5 U.S.C. 551557 (1976); Federal Power Act, as amended, 16 U.S.C. 291-628 (1976 & Supp. V 1981), Dept. of Energy Organization Act 42 U.S.C. 7101-7352 (Supp. V 1981); E.O. 12009, 3 CFR 142 (1978)) [Order 141, 12 FR 8485, Dec. 19, 1947, as amended by Order 344, 48 FR 49010, Oct. 24, 1983]

§4.13 Time for filing protest.

Thirty days after service thereof will be allowed to the licensee within which to file a protest to such report.

« AnteriorContinuar »