§ 284.263 Exemption from section 7 of Natural Gas Act and certain regulatory conditions.

Any participant that engages in an emergency natural gas transaction conducted in accordance with this subpart is exempt from the requirements of section 7 of the Natural Gas Act and the conditions of §284.7, except as provided in §284.266, and from the requirements of §§ 284.8-284.13 of subpart A of this part. Participation in any emergency natural gas transaction will not subject any participant to the jurisdiction of the Commission under section 7 of the Natural Gas Act except to the extent such transaction is provided for in this subpart.

§ 284.264 Terms and conditions.

(a) General conditions. (1) A participant must make every reasonable attempt to minimize use of emergency natural gas transactions.

(2) Before deliveries of emergency natural gas commence, a responsible official of the recipient must provide any participants in the emergency natural gas transaction sufficient information to enable the participants to form a good faith belief that an emergency exists or is imminent.

(3) No participant may engage in an emergency natural gas transaction if its participation will adversely affect service to its existing customers.

(4) A participant may not sell emergency natural gas if, during the term of the sale, it is also purchasing emergency natural gas under this subpart, except when natural gas is being sold to relieve an emergency on another, separate segment of the participant's system.

(5) An interstate pipeline, acting in an emergency gas transaction as a broker or agent on behalf of another participant or any other person, may not receive compensation for such brokerage or agency service.

(6) A recipient of emergency natural gas that directly benefits from the service must:

(1) Provide line loss and the fuel volumes required to transport the emergency natural gas; and

(ii) Pay for the facilities required to be constructed to conduct the emergency natural gas transaction.

(b) Duration—(1) Emergency sale or transportation. An emergency natural gas transaction is limited to 60 consecutive calender days, except that such transaction may be continued for an additional 60 consecutive days if:

(i) Fifteen days prior to the end of the initial 60-day period, the recipient of emergency natural gas files a petition that:

(A) Describes fully the continued emergency,

(B) Requests a waiver of the intitial 60-day limitation and permission for an extension of the transaction for an additional 60 days; and

(ii) Within the 15-day period, the Commission does not, by order, prohibit continuation of the emergency natural gas transaction for the additional 60-day period.

(2) Redelivery in emergency exchange. The redelivery of emergency natural gas received under an exchange arrangement must occur within 180 consecutive days following the termination of deliveries of the emergency natural gas.

§ 284.265 Cost recovery by interstate pipeline.

(a) Except as provided in paragraph (b), an interstate pipeine that provides emergency natural gas, whether from its system supply or by special purchase, must directly assign the emergency gas costs to the recipient.

(b) If an interstate pipeline cannot identify individual recipients, the interstate pipeline must roll the emergency gas costs into its general system supply costs.

[blocks in formation]

(1) Base its rates upon the methodology used in designing rates to recover the transmission and related storage costs included in one of its then-effective sales rates schedules; or

(ii) Use the rates contained in one of its transportation rate schedules on file with the Commission which the interstate pipeline determines covers service comparable to transportation service authorized under this subpart.

(b) Interstate pipeline costs excluded from rate base. An interstate pipeline may not include in its jurisdictional rate base any cost associated with facilities installed and operated in connection with an emergency natural gas transaction unless a certificate of public convenience and necessity has been issued authorizing the costs. Absent a certificate, such facilities may only be used to conduct emergency natural gas transactions or transactions authorized under section 311 of the NGPA.

[Order 449, 51 FR 9187, Mar. 18, 1986, as amended by Order 581, 60 FR 53074, Oct. 11, 1995]

§ 284.267 Intrastate pipeline emergency transportation rates.

General rule. Rates and charges for transportation of emergency gas by intrastate pipelines authorized under this subpart must be determined in accordance with § 284.123 of this chapter.

§ 284.268 Local distribution company emergency transportation rates.

(a) Rate on file. A local distribution company that has a rate on file with an appropriate state regulatory agency for city-gate transportation services must determine its rates and charges for transportation of emergency natural gas in accordance with §284.123 of this chapter.

(b) Rate not on file. A local distribution company that does not have a rate on file with an appropriate state regulatory agency for city-gate transportation services must determine its rates and charges for transportation of emergency natural gas (per unit volume of emergency natural gas transported) in accordance § 284.224(e)(2)(ii) of this chapter.

with

[blocks in formation]

(1) That the report is submitted pursuant to §284.270 for an emergency natural gas transaction;

(2) The date deliveries commenced;

(3) The specific nature of the situation, explained in sufficient detail to demonstrate how the situation qualifies as an emergency under § 284.262 and under the conditions of §284.264, and anticipated duration of the emergency;

(4) The estimated total amount and average daily amount of emergency natural gas to be purchased during the term of the transaction;

(5) The purchase price of the emergency natural gas;

(6) The transportation rate; and (7) The identity of all participants involved in the transaction, including any customers to whom the emergency natural gas is to be assigned.

(b) Forty-eight hour report for transportation (excluding exchanges). Within 48 hours after deliveries commence in an emergency natural gas transaction which does not involve the sale of emergency natural gas, the recipient of emergency natural gas shall notify the Commission by telegram or other written report of the transportation, stating, in the following sequence:

(1) That the report is submitted pursuant to § 284.270 for an emergency transaction;

(2) The date deliveries commenced; (3) The specific nature of the situation, explained in sufficient detail to

demonstrate how the situation qualifies as an emergency under § 284.262 and under the conditions of § 284.264, and anticipated duration of the emergency;

(4) The estimated total amount and average daily amount of emergency natural gas to be transported during the term of the transaction;

(5) The transportation rate; and (6) The identity of all the participants involved in the transaction.

(c) Forty-eight hour report for exchanges. Within 48 hours after an exchange transaction for emergency natural gas commences, the initial recipient of the exchange volumes must notify the Commission by telegram or other written report of the exchange, stating, in the following sequence:

(1) That the report is for and submitted pursuant to §284.270 for an emergency transaction;

(2) The date the exchange commenced;

(3) The specific nature of the situation, explained in sufficient detail to clearly demonstrate how the situation qualifies as an emergency under § 284.262 and under the conditions of § 284.264, and anticipated duration of the emergency;

(4) The estimated total amount and average daily amount of emergency natural gas to be exchanged during the term of the transaction;

(5) The identity of all participants involved in the transaction;

(6) Whether the exchange is simultaneous or deferred, or any imbalances in the volumes;

(7) Whether the exchange is on a thermal or volumetric basis; and

(8) The rates or charges, if any, for the exchange service.

(d) Termination report. Within thirty days after the emergency natural gas transaction ends, the participant that received the emergency natural gas shall file with the Commission a sworn statement and two conformed copies thereof, which must include the following information in the following sequence:

(1) A description of the emergency natural gas transaction, including sufficient information to clearly demonstrate how the situation qualifies as an emergency under § 284.262 and under the conditions of §284.264; the com

mencement and termination dates; the date of the 48-hour report, and the method of resolving the emergency;

(2) Any corrections to the 48-hour report information supplied to the Commission under paragraphs (a) through (c) of this section or a statement that the information was correct;

(3) The volumes of the emergency natural gas delivered during the transaction;

(4) The total compensation received by the seller for the emergency sale;

(5) The total compensation paid for the emergency natural gas transportation or exchange service, if any;

(6) The methods by which such compensation was derived;

(7) The total volumes of natural gas whose cost was assigned to specific customers, and the total volumes whose cost was included in system supply; (8) The information supplied to any other participant pursuant to

§ 284.264(a)(2); and

(9) A statement that the emergency natural gas transaction was carried out in accordance with this subpart, and that identifies the circumstances demonstrating an emergency existed or was imminent so as to require an emergency natural gas transaction.

§ 284.271 Waiver.

The Commission may, by order, waive the requirements of this subpart in connection with any emergency natural gas transaction to the extent required by the public interest.

Subpart J-Blanket Certificates

Authorizing Certain Natural Gas Sales by Interstate Pipelines

SOURCE: Order 636, 57 FR 13318, Apr. 16, 1992, unless otherwise noted.

§ 284.281 Applicability.

This subpart applies to any interstate pipeline that offers transportation service under subpart B or G of this part.

$284.282 Definitions.

(a) Bundled sales service is gas sales service that is not sold separately from transportation service.

(b) Sales service includes firm or interruptible gas sales.

(c) Unbundled sales service is gas sales service that is sold separately from transportation service.

(d) Small customer is a customer that purchases gas from a pipeline under the pipeline's one-part imputed load factor rate schedule on the effective date of the blanket certificate.

[Order 636, 57 FR 13318, Apr. 16, 1992, as amended by Order 636-A, 57 FR 36218, Aug. 12, 1992]

§ 284.283 Point of unbundling.

A sales service is unbundled when gas is sold at a point before it enters a mainline system, at an entry point to a mainline system from a production area, or at an intersection with another pipeline system.

§ 284.284 Blanket

certificates for unbundled sales services.

(a) Authorization. An interstate pipeline that offers transportation service under subpart B or G of this part is granted a blanket certificate of public convenience and necessity pursuant to section 7 of the Natural Gas Act authorizing it to provide unbundled firm or interruptible sales in accordance with the provisions of this section.

(b) Conversion to unbundled firm sales service and firm transportation service. On the effective date of the pipeline's blanket certificate for unbundled sales services under paragraph (a) of this section, firm sales entitlements under any firm sales service agreement for a bundled sales service are converted to an equivalent amount of unbundled firm sales service and an equivalent amount of unbundled firm transportation service.

(c) Conversion to unbundled interruptible sales service and interruptible transportation service. On the effective date of the pipeline's blanket certificate for unbundled sales services under paragraph (a) of this section, interruptible sales volumes under any interruptible sales service agreement for a bundled sales service are converted to an equivalent amount of unbundled sales service and an equivalent amount of unbundled interruptible transportation service.

(d) A pipeline that provides unbundled sales service under this section may serve as an agent of the sales customer to arrange for any pipelineprovided service necessary to deliver gas to the customer.

(e) Small customer cost-based rate. A pipeline that provided bundled sales service to a small customer before the effective date of the blanket certificate granted in paragraph (a) of this section is required to offer a sales service to that customer at a cost-based rate for one year from the effective date of the certificate. The obligation to sell at the cost-based rate expires one year after the effective date of the certificate.

[Order 636, 57 FR 13318, Apr. 16, 1992, as amended by Order 636-A, 57 FR 36218, Aug. 12, 1992; Order 581, 60 FR 53074, Oct. 11, 1995]

§ 284.285 Pregrant of abandonment of unbundled sales services.

Abandonment of unbundled sales services is authorized pursuant to section 7(b) of the Natural Gas Act upon the expiration of the contractual term or upon termination of each individual sales arrangement authorized under § 284.284.

§ 284.286 Standards of conduct for unbundled sales service.

(a) To the maximum extent practicable, the pipeline must organize its unbundled sales and transportation operating employees so that they function independently of each other.

(b) The pipeline must conduct its business to conform to the requirements set forth in §284.8(b)(2) and § 284.9(b)(2) with respect to the equality of service by not giving shippers of gas sold by the pipeline any preference over shippers of gas sold by any other merchant in matters relating to part 284 transportation.

(c) The pipeline must comply with §§ 161.3 (a), (b), (d), and (k) of this chapter and comply with §§ 161.3 (c), (e), (f), (g), and (h) of this chapter by considering its unbundled sales operating employees as an operational unit which is the functional equivalent of a marketing affiliate.

(d) The pipeline must comply with § 250.16 of this chapter by considering

its unbundled sales operating employees as an operational unit which is the functional equivalent of a marketing affiliate.

(e) A pipeline that provides unbundled sales service under §284.284 must have tariff provisions on file with the Commission indicating how the pipeline is complying with the standards of this section.

[Order 636, 57 FR 13318, Apr. 16, 1992, as amended by Order 566, 59 FR 32899, June 27, 1994; Order 581, 60 FR 53074, Oct. 11, 1995]

§ 284.287 Implementation and effective date.

(a) Prior to offering any sales service under this subpart J, a pipeline must file revised tariff sheets incorporating the provisions of this subpart J.

(b) A blanket certificate issued under § 284.284 will be effective on the effective date (as approved by the Commission) of the tariff sheets implementing service under that certificate.

[Order 581, 60 FR 53074, Oct. 11, 1995]

§ 284.288 Reporting requirements. Interstate pipelines engaging in sales under a certificate granted under § 284.284 must file with the Commission by March 1 of each year, an annual report for the preceding calendar year describing for each transaction the identities of the parties, the type of service provided (firm or interruptible), the total volumes sold, and the total revenues received. The report must be signed under oath by a senior official of the company.

Subpart K-Transportation af Natu

ral Gas on the Outer Continental Shelf by Interstate Natural Gas Pipelines on Behalf of Others

SOURCE: Order 509, 53 FR 50938, Dec. 19, 1988, unless otherwise noted.

§ 284.301 Applicability.

This subpart implements section 5 of the Outer Continental Shelf Land Act (OCSLA) and applies to any jurisdictional interstate natural gas pipeline that holds a certificate under section 7 of the Natural Gas Act (NGA) authorizing the construction and operation of

facilities on the Outer Continental Shelf (OCS).

§ 284.302 Definitions.

For the purposes of this subpart, the term:

(a) Outer Continental Shelf (OCS) has the same meaning as found in section 2(a) of the OCSLA (43 U.S.C. 1331(a)); and

(b) OCS pipeline means an interstate natural gas pipeline that holds a certificate under section 7 of the NGA authorizing the construction and operation of facilities on the OCS, and includes all of the OCS pipeline's facilities that fall within the scope of the Commission's jurisdiction under section 7 of the NGA to the full extent that such facilities are used or necessary to transport natural gas on or across the OCS between:

(1) Any locations on the OCS (if the pipeline does not have an interconnection off the OCS), or

(2) The OCS and the first point of interconnection on the shoreward side of the OCS where the pipeline delivers or receives natural gas to or from either:

(1) A natural gas conditioning or processing facility, or

(ii) Another pipeline, or

(iii) A distributor or end user of natural gas.

[Order 509, 53 FR 50938, Dec. 19, 1988, as amended by Order 509-A, 54 FR 8313, Feb. 28, 1989]

§ 284.303 OCS blanket certificates.

Every OCS pipeline [as that term is defined in §284.302(b)] is required to provide open-access, nondiscriminatory transportation service pursuant to a blanket transportation certificate issued under subpart G of this part. [Order 559, 58 FR 52663, Oct. 12, 1993]

Subpart L-Certain Sales for Resale by Non-interstate Pipelines § 284.401 Definitions.

Affiliated marketer. For purposes of this subpart, an "affiliated marketer” is a person engaged in the "marketing" of natural gas that is an "affiliate" of

« AnteriorContinuar »