Hope Natural Gas Company, Petitioner, Vs. Federal Power Commission, City of Cleveland, City of Akron, and Pennsylvania Public Utility Commission, Respondents, Volumen2Gates Legal Publishing Company, 1941 |
Contenido
STATEMENT | 1 |
A The operating expense allowances and credits to operating | 7 |
f Total credit to Hope operating expenses for excess | 13 |
Otras 7 secciones no mostradas
Otras ediciones - Ver todas
Hope Natural Gas Company, Petitioner, Vs. Federal Power Commission ..., Volumen5 Hope Natural Gas Company Vista de fragmentos - 1941 |
Hope Natural Gas Company, Petitioner, Vs. Federal Power Commission ..., Volumen3 Hope Natural Gas Company Vista de fragmentos - 1941 |
Hope Natural Gas Company, Petitioner, Vs. Federal Power Commission ..., Volumen1 Hope Natural Gas Company Vista de fragmentos - 1941 |
Términos y frases comunes
accrued depreciation actual adjusted book cost allocated to East allowance amount Appendix average basis capital cents per M.c.f. charged City of Cleveland coke oven gas Commission accountants Commission counsel Commission staff's Commission's staff Company's properties complaint Compressor Station Construction and Refining December 31 depreciation and depletion depreciation reserve determined Docket drilling Dunn East Ohio Gas equipment estimate export fair value Federal Income Tax Federal Power Act Federal Power Commission field line French gas purchased Gas Sales gasolene and butane Hope company Hope Construction Hope Natural Gas Hope-East Ohio rate included Interstate Interstate Commerce Commission investment rate base June 30 Lyon Natural Gas Act Natural Gas Company Ohio Gas Company original cost pany pipe lines present production prudent investment rate Public Utilities Commission rate of return reasonable Refining Company reproduction cost revenues Rhodes service lives Soyster Staff Brief tion Tonkin transmission unoperated acreage West Virginia witness