tion is awarded prior to October 1, 1984; and

(iii) The phase or segment that receives 75 percent funding is necessary to (A) make a phase or segment previously funded by EPA operational and comply with the enforceable requirements of the Act, or (B) complete the treatment works referenced in (a)(3)(i) of this section provided that all phases or segments previously funded by EPA are operational and comply with the enforceable requirements of the Act.

(b) Innovative and alternative technology. In accordance with § 35.2032, the Federal share for eligible treatment works or unit processes and techniques that the Regional Administrator determines meet the definition of innovative or alternative technology shall be 20 percent greater than the Federal share under paragraph (a) or (c) of this section, but in no event shall the total Federal share be greater than 85 percent. This increased Federal share depends on the availability of funds from the reserve under § 35.2020. The proportional State contribution to the non-Federal share of building costs for I/A projects must be the same as or greater than the proportional State contribution (if any) to the non-Federal share of eligible building costs for all treatment works which receive 75 or 55 percent grants or such other Federal share under paragraph (c) of this section in the State.

(c) Uniform lower Federal share. (1) Except as provided in § 35.2032 (c) and (d) of this section, the Governor of a State may request the Regional Administrator's approval to revise uniformly throughout the State the Federal share of grant assistance for all future projects. The revised Federal share must apply to all needs categories (see § 35.2015(b)(2)).

(2) After EPA awards grant assistance for a project, the Federal share shall be the same for any grant increase that is within the scope of the project.

(3) The uniform lower Federal share established by the Governor does not apply to projects funded under § 35.2024(b).

(d) Training facilities. The Federal share of treatment works required to

train and upgrade waste treatment works operations and maintenance personnel may be up to 100 percent of the allowable cost of the project.

(1) Where a grant is made to serve two or more States, the Administrator is authorized to make an additional grant for a supplemental facility in each State. The Federal funds awarded to any State under section 109(b) for all training facilities shall not exceed $500,000.

(2) Any grantee who received a grant under section 109(b) before December 27, 1977, may have the grant increased up to $500,000 by funds made available under the Act, not to exceed 100 percent of the allowable costs.

(Approved by the Office of Management and Budget under control number 20400027)

[49 FR 6234, Feb. 17, 1984, as amended at 50 FR 45896, Nov. 4, 1985]

§ 35.2200 Grant conditions.

In addition to the EPA General Grant Conditions (Part 30 of this subchapter), each treatment works grant shall be subject to the conditions under §§ 35.2202 through 35.2218.

§ 35.2202 Step 2+3 projects.

(a) Prior to initiating action to acquire eligible real property, a Step 2+3 grantee shall submit for Regional Administrator review and written approval the information required under § 35.2040(b)(7).

(b) Before initiating procurement action for the building of the project, a Step 2+3 grantee shall submit for the Regional Administrator's review and written approval the information required under §§ 35.2040(b) (5) and (6), 35.2106, 35.2107, 35.2130 and 35.2140.

§ 35.2204 Project changes.

(a) Minor changes in the project work that are consistent with the objectives of the project and within the scope of the grant agreement do not require the execution of a formal grant amendment before the grantee's implementation of the change. However, the amount of the funding provided by the grant agreement may only

be increased by a formal grant amendment.

(b) The grantee must receive from the Regional Administrator a formal grant amendment before implementing changes which:

(1) Alter the project performance standards;

(2) Alter the type of wastewater treatment provided by the project;

(3) Significantly delay or accelerate the project schedule;

(4) Substantially alter the facilities plan, design drawings and specifications, or the location, size, capacity, or quality of any major part of the project; or

(5) Otherwise require a formal grant amendment under Part 30 of this subchapter.

§ 35.2205 Maximum allowable project cost.

(a) Grants awarded on or after the effective date of this regulation. Except as provided in paragraph (c) of this section, for Step 2+3 or Step 3 grants awarded on or after the effective date of this regulation, the maximum allowable project cost will be the sum of:

(1) The allowable cost of the following:

(i) The initial award amount of all project subagreements between the grantee and its contractors;

(ii) The initial amounts approved for force account work to be performed on the project;

(iii) The purchase price of eligible real property; and

(iv) The initial amount approved for project costs not included under paragraphs (a)(1)(i) through (a)(1)(iii) of this section, excluding any amounts approved for an allowance under § 35.2025 and for contingencies; and

(2) Five percent of the sum of the amounts included under paragraphs (a)(1)(i) through (a)(1)(iv) of this section.

(b) Grants awarded before the effective date of the regulation. Except as provided in paragraph (c) of this section, for Step 2+3 or Step 3 grants awarded before the effective date of this regulation, the maximum allowable increase in the cost for work covered by each subagreement finally advertised or, where there will be no ad

vertisement,

each subagreement awarded on or after the effective date of this regulation will be five percent of the initial award amount of the subagreement.

(c) Differing site conditions. In determining whether the maximum allowable project cost or increase in subagreement cost will be exceeded, costs of equitable adjustments for differing site conditions will be exempt, provided the requirements of 40 CFR Part 35, Subpart I, Appendix A, paragraph A.1.g. and all other applicable laws and regulations have been met. [50 FR 46649, Nov. 12, 1985]

§ 35.2206 Operation and maintenance.

(a) The grantee must assure economical and effective operation and maintenance (including replacement) of the treatment works.

(b) Except as provided in paragraphs (c) (1) and (2) of this section, the Regional Administrator shall not pay more than 50 percent of the Federal share of any project unless the grantee has furnished and the Regional Administrator has approved the final plan of operation required by

§ 35.2106, and shall not pay more than 90 percent of the Federal share of any project unless the grantee has furnished and the Regional Administrator has approved an operation and maintenance manual.

(c)(1) In projects where segmenting of a proposed treatment works has occurred, the Regional Administrator shall not pay more than 90 percent of the Federal share of the total allowable costs of the proposed treatment works until the grantee has furnished and the Regional Administrator has approved an operation and maintenance manual.

(2) In projects where a component is placed in operation before completion of the entire project, the Regional Administrator shall not make any additional payment on that project until a final operation and maintenance manual for the operating component is furnished and approved.

(Approved by the Office of Management and Budget under control number 20400027)

§ 35.2208 Adoption of sewer use ordinance and user charge system.

The grantee shall adopt its sewer use ordinance and implement its user charge system under developed §§ 35.2130 and 35.2140 before the treatment works is placed in operation. Further, the grantee shall implement the user charge system and sewer use ordinance for the useful life of the treatment works.

§ 35.2210 Land acquisition.

The grantee shall not acquire real property determined allowable for grant assistance until the Regional Administrator has determined that applicable provisions of 40 CFR Part 4 have been met.

§ 35.2211 Field testing for Innovative and Alternative Technology Report.

The grantee shall submit a report containing the procedure, cost, results and conclusions of any field testing. The report shall be submitted to the Regional Administrator in accordance with a schedule to be specified in the grant agreement.

(Approved by the Office of Management and Budget under control number 20400027)

§ 35.2212 Project initiation.

(a) The grantee shall expeditiously initiate and complete the project, in accordance with the project schedule contained in the grant application and agreement. Failure to promptly initiate and complete a project may result in the imposition of sanctions under Part 30 of this chapter.

(b) The grantee shall initiate procurement action for building the project promptly after award of a Step 3 grant or after receiving written approval of the information required under 35.2202 under a Step 2+3 grant. Public notice of proposed procurement action should be made promptly after Step 3 award or final approvals for a Step 2+3 grant under § 35.2202. The grantee shall award the subagreement(s) and issue notice(s) to proceed, where required, for building all significant elements of the project within twelve months of the Step 3 award or final Step 2+3 approvals.

(c) Failure to promptly award all subagreement(s) for building the project will result in a limitation on allowable costs. (See Appendixes A, A.2.e.).

(d) The grantee shall notify the Regional Administrator immediately upon award of the subagreement(s) for building all significant elements of the project (see 40 CFR 33.211).

(Approved by the Office of Management and Budget under control number 20400027)

§ 35.2214 Grantee responsibilities.

(a) The grantee shall complete the project in accordance with the grant agreement including: The facilities plan that establishes the need for the project; the design drawings and specifications; the plan of operation under § 35.2106 that identifies the basis to determine annual operating costs; the financial management system under § 35.2140(d) that adequately accounts for revenues and expenditures; the user charge system under § 35.2140 that will generate sufficient revenue to operate and maintain the treatment works; the project schedule; and all other applicable regulations. The grantee shall maintain and operate the project to meet project performance standards including the enforceable requirements of the Act for the design life.

(b) The grantee shall provide the architectural and engineering services and other services necessary to fulfill the obligation in paragraph (a) of this section.

§ 35.2216 Notice of building completion and final inspection.

The grantee shall notify the Regional Administrator when the building of the project is complete. Final inspection shall be made by the Regional Administrator after receipt of the notice of building completion.

(Approved by the Office of Management and Budget under control number 20400027)

§ 35.2218 Project performance.

(a) The grantee shall notify the Regional Administrator in writing of the actual date of initiation of operation.

(b) Subject to the provisions of 40 CFR Part 33, the grantee shall select the engineer or engineering firm principally responsible for either supervising construction or providing architectural and engineering services during construction as the prime engineer to provide the following services during the first year following the initiation of operation:

(1) Direct the operation of the project and revise the operation and maintenance manual as necessary to accommodate actual operating experi

ence;

(2) Train or provide for training of operating personnel and prepare curricula and training material for operating personnel; and

(3) Advise the grantee whether the project is meeting the project performance standards.

(c) On the date one year after the initiation of operation of the project, the grantee shall certify to the Regional Administrator whether the project meets the project performance standards. If the Regional Administrator or the grantee concludes that the project does not meet the project performance standards, the grantee shall submit the following:

(1) A corrective action report which includes an analysis of the cause of the project's failure to meet the performance standards (including the quantity of infiltration/inflow proposed to be eliminated), and an estimate of the nature, scope and cost of the corrective action necessary to bring the project into compliance;

(2) The schedule for undertaking in a timely manner the corrective action necessary to bring the project into compliance; and

(3) The scheduled date for certifying to the Regional Administrator that the project is meeting the project performance standards.

(d) Except as provided in § 35.2032(c) the grantee shall take corrective action necessary to bring a project into compliance with the project performance standards at its own expense.

(e) Nothing in this section:

(1) Prohibits a grantee from requiring more assurances, guarantees, or indemnity or other contractual require

ments from any party performing project work; or

(2) Affects EPA's right to take remedial action, including enforcement, against a grantee that fails to carry out its obligations under § 35.2214. (Approved by the Office of Management and Budget under control number 20400027)

§ 35.2250 Determination of allowable costs.

The Regional Administrator will determine the allowable costs of the project based on applicable provisions of laws and regulations, the scope of the approved project, § 30.705 of this subchapter, and Appendix A of this subpart.

§ 35.2260 Advance purchase of eligible land.

In the case of grant assistance awarded solely for the acquisition of eligible land, the following provisions are deferred until the award of the ensuing Step 3 assistance for the building of facilities: §§ 35.2105, 35.2130, 35.2140, 35.2206 and 35.2208.

§ 35.2262 Funding of field testing.

In the case of grant assistance for field testing of innovative or alternative wastewater process and techniques, the following provisions are deferred until the award of assistance for building the approved facilities: §§ 35.2105, 35.2106, 35.2122, 35.2130, 35.2140, 35.2206, and 35.2208.

§ 35.2300 Grant payments.

Except as provided in § 35.2206, the Regional Administrator shall pay the Federal share of the allowance under § 35.2025 and the allowable project costs incurred to date and currently due and payable by the grantee, as certified in the grantee's most recent payment request.

(a) Adjustment. The Regional Administrator may at any time review and audit requests for payment and payments and make appropriate adjustments as provided in Part 30 of this chapter.

(b) Refunds, rebates and credits. The Federal share of any refunds, rebates, credits, or other amounts (including

any interest) that accrue to or are received by the grantee for the project, and that are properly allocable to costs for which the grantee has been paid under a grant, must be credited to the current State allotment or paid to the United States. Examples include rebates for prompt payment and sales tax refunds. Reasonable expenses incurred by the grantee securing such refunds, rebates, credits, or other amounts shall be allowable under the grant when approved by the Regional Administrator.

(c) Release. By its acceptance of final payment, the grantee releases and discharges the United States, its officers, agents, and employees from all liabilities, obligations, and claims arising out of the project work or under the grant, subject only to exceptions previously specified in writing between the Regional Administrator and the grantee.

(d) Payment of costs incurred under the Uniform Relocation Assistance and Real Property Acquisition Policies Act. Notwithstanding the provisions of the introductory paragraph of this section, if the Regional Administrator determines it is necessary for the expeditious completion of a project, he may make advance payment after grant award for the Federal share of the eligible cost of any payment of relocation assistance under § 4.502(c) of this chapter by the grantee. The requirements in Part 30 of this subchapter apply to any advances of funds for assistance payments.

(e) Payment under grants to States for advances of allowance-(1) Advance payment to State. Notwithstanding the provisions of the introductory paragraph of this section, the Regional Administrator, under a State grant for advances of allowance (see § 35.2025), may make payments on an advance or letter-of-credit payment method in accordance with the requirements under Part 30 of this chapter. The State and the Regional Administrator shall agree to the payment terms.

(2) Assignment. If the State chooses to assign its payments to a potential grant applicant, it shall execute an agreement with the potential grant applicant authorizing direct payment

from EPA and establishing appropriate terms for payment. The State shall provide a copy of the agreement to EPA.

(Approved by the Office of Management and Budget under control number 20400027)

§ 35.2350 Subagreement enforcement.

(a) Regional Administrator authority. At the grantee's request the Regional Administrator may provide technical and legal assistance in the administration and enforcement of any subagreement related to treatment works for which an EPA grant was made and to intervene in any civil action involving the enforcement of such subagreements, including subagreement disputes which are the subject of either arbitration or court action.

(b) Privity of subagreement. The Regional Administrator's technical or legal involvement in any subagreement dispute will not make EPA a party to any subagreement entered into by the grantee.

(c) Grantee responsibilities. The provision of technical or legal assistance under this section in no way releases the grantee from its obligations under § 35.2214, or affects EPA's right to take remedial action, including enforcement, against a grantee that fails to carry out those obligations.

APPENDIX A-DETERMINATION OF
ALLOWABLE COSTS

(a) Purpose. The information in this appendix represents Agency policies and procedures for determining the allowability of project costs based on the Clean Water Act, EPA policy, appropriate Federal cost principles under Part 30 of this subchapter and reasonableness.

(b) Applicability. This cost information applies to grant assistance awarded on or after the effective date of this regulation. Project cost determinations under this subpart are not limited to the items listed in this appendix. Additional cost determinations based on applicable law and regulations must of course be made on a projectby-project basis. Those cost items not previously included in program requirements are not mandatory for decisions under grants awarded before the effective date. They are only to be used as guidance in those cases.