connection with, bringing the complaint regarding the reprisal, as determined by the head of the executive agency.

(2) Whenever a person fails to comply with an order issued under paragraph (1), the head of the executive agency shall file an action for enforcement of such order in the United States district court for a district in which the reprisal was found to have occurred. In any action brought under this paragraph, the court may grant appropriate relief, including injunctive relief and compensatory and exemplary damages.

(3) Any person adversely affected or aggrieved by an order issued under paragraph (1) may obtain review of the order's conformance with this subsection, and any regulations issued to carry out this section, in the United States court of appeals for a circuit in which the reprisal is alleged in the order to have occurred. No petition seeking such review may be filed more than 60 days after issuance of the order by the head of the agency. Review shall conform to chapter 7 of title 5, United States Code.

(d) CONSTRUCTION.-Nothing in this section may be construed to authorize the discharge of, demotion of, or discrimination against an employee for a disclosure other than a disclosure protected by subsection (a) or to modify or derogate from a right or remedy otherwise available to the employee.

(e) DEFINITIONS.-In this section:

(1) The term "contract" means a contract awarded by the head of an executive agency.

(2) The term "contractor" means a person awarded a contract with an executive agency.

(3) The term "Inspector General" means an Inspector General appointed under the Inspector General Act of 1978.

SEC. 316. [41 U.S.C. 266] MERIT-BASED AWARD OF GRANTS FOR RESEARCH AND DEVELOPMENT.

(a) POLICY.-It is the policy of Congress that an executive agency should not be required by legislation to award a new grant for research, development, test, or evaluation to a non-Federal Government entity. It is further the policy of Congress that any program, project, or technology identified in legislation be awarded through merit-based selection procedures.

(b) RULE OF CONSTRUCTION.-A provision of law may not be construed as requiring a new grant to be awarded to a specified non-Federal Government entity unless that provision of law

(1) specifically refers to this subsection;

(2) specifically identifies the particular non-Federal Government entity involved; and

(3) specifically states that the award to that entity is required by such provision of law in contravention of the policy set forth in subsection (a).

(c) NEW GRANT DEFINED.-For purposes of this section, a grant is a new grant unless the work provided for in the grant is a continuation of the work performed by the specified entity under a preceding grant.

(d) INAPPLICABILITY TO CERTAIN GRANTS. This section shall not apply with respect to any grant that calls upon the National Academy of Sciences to investigate, examine, or experiment upon any subject of science or art of significance to an executive agency

and to report on such matters to Congress or any agency of the Federal Government.

SEC. 317. [41 U.S.C. 266a] SHARE-IN-SAVINGS CONTRACTS.

(a) AUTHORITY TO ENTER INTO SHARE-IN-SAVINGS CONTRACTS. (1) The head of an executive agency may enter into a share-in-savings contract for information technology (as defined in section 11101(6) of title 40, United States Code) in which the Government awards a contract to improve mission-related or administrative processes or to accelerate the achievement of its mission and share with the contractor in savings achieved through contract performance.

(2)(A) Except as provided in subparagraph (B), a share-in-savings contract shall be awarded for a period of not more than five years. (B) A share-in-savings contract may be awarded for a period greater than five years, but not more than 10 years, if the head of the agency determines in writing prior to award of the contract that

(i) the level of risk to be assumed and the investment to be undertaken by the contractor is likely to inhibit the government from obtaining the needed information technology competitively at a fair and reasonable price if the contract is limited in duration to a period of five years or less; and

(ii) usage of the information technology to be acquired is likely to continue for a period of time sufficient to generate reasonable benefit for the government.

(3) Contracts awarded pursuant to the authority of this section shall, to the maximum extent practicable, be performance-based contracts that identify objective outcomes and contain performance standards that will be used to measure achievement and milestones that must be met before payment is made.

(4) Contracts awarded pursuant to the authority of this section shall include a provision containing a quantifiable baseline that is to be the basis upon which a savings share ratio is established that governs the amount of payment a contractor is to receive under the contract. Before commencement of performance of such a contract, the senior procurement executive of the agency shall determine in writing that the terms of the provision are quantifiable and will likely yield value to the Government.

(5)(A) The head of the agency may retain savings realized through the use of a share-in-savings contract under this section that are in excess of the total amount of savings paid to the contractor under the contract, but may not retain any portion of such savings that is attributable to a decrease in the number of civilian employees of the Federal Government performing the function. Except as provided in subparagraph (B), savings shall be credited to the appropriation or fund against which charges were made to carry out the contract and shall be used for information technology. (B) Amounts retained by the agency under this subsection shall

(i) without further appropriation, remain available until expended; and

(ii) be applied first to fund any contingent liabilities associated with share-in-savings procurements that are not fully funded.

(b) CANCELLATION AND TERMINATION.-(1) If funds are not made available for the continuation of a share-in-savings contract entered into under this section in a subsequent fiscal year, the contract shall be canceled or terminated. The costs of cancellation or termination may be paid out of—

(A) appropriations available for the performance of the contract;

(B) appropriations available for acquisition of the information technology procured under the contract, and not otherwise obligated; or

(C) funds subsequently appropriated for payments of costs of cancellation or termination, subject to the limitations in paragraph (3).

(2) The amount payable in the event of cancellation or termination of a share-in-savings contract shall be negotiated with the contractor at the time the contract is entered into.

(3)(A) Subject to subparagraph (B), the head of an executive agency may enter into share-in-savings contracts under this section in any given fiscal year even if funds are not made specifically available for the full costs of cancellation or termination of the contract if funds are available and sufficient to make payments with respect to the first fiscal year of the contract and the following conditions are met regarding the funding of cancellation and termination liability:

(i) The amount of unfunded contingent liability for the contract does not exceed the lesser of

(I) 25 percent of the estimated costs of a cancellation or termination; or

(II) $5,000,000.

(ii) Unfunded contingent liability in excess of $1,000,000 has been approved by the Director of the Office of Management and Budget or the Director's designee.

(B) The aggregate number of share-in-savings contracts that may be entered into under subparagraph (A) by all executive agencies to which this chapter applies in a fiscal year may not exceed 5 in each of fiscal years 2003, 2004, and 2005.

(c) DEFINITIONS.-In this section:

(1) The term "contractor" means a private entity that enters into a contract with an agency.

(2) The term "savings" means—

(A) monetary savings to an agency; or

(B) savings in time or other benefits realized by the agency, including enhanced revenues (other than enhanced revenues from the collection of fees, taxes, debts, claims, or other amounts owed the Federal Government).

(3) The term "share-in-savings contract" means a contract under which

(A) a contractor provides solutions for

(i) improving the agency's mission-related or administrative processes; or

(ii) accelerating the achievement of agency missions; and

(B) the head of the agency pays the contractor an amount equal to a portion of the savings derived by the agency from

(i) any improvements in mission-related or administrative processes that result from implementation of the solution; or

(ii) acceleration of achievement of agency missions.

(d) TERMINATION.-No share-in-savings contracts may be entered into under this section after September 30, 2005.

[blocks in formation]

OFFICE OF FEDERAL PROCUREMENT POLICY ACT