Committee Report on Debarment and Suspension of Persons from Government Contracting and Federally Assisted Construction WorkU.S. Government Print., 1962 - 147 páginas |
Dentro del libro
Resultados 1-5 de 46
Página 7
... individual or firm from the contracts or subcomtracts of a government department or agency or from participating in any federally assisted construction work should be preceded by ( i ) notice of proposed debarment to the parties in ...
... individual or firm from the contracts or subcomtracts of a government department or agency or from participating in any federally assisted construction work should be preceded by ( i ) notice of proposed debarment to the parties in ...
Página 8
... individual rejection of any bid or proposal , the procedures for which are set forth in Recommendation 4 . Recommendation 2 : ( a ) In cases of criminal conviction or civil judgment affect- ing an individual's or firm's present ...
... individual rejection of any bid or proposal , the procedures for which are set forth in Recommendation 4 . Recommendation 2 : ( a ) In cases of criminal conviction or civil judgment affect- ing an individual's or firm's present ...
Página 9
... individual or firm concerned would be substantially harmful to the Government's law enforcement activities or to the success- ful criminal or civil prosecution of such individual or firm . If the Attorney General or his designee makes ...
... individual or firm concerned would be substantially harmful to the Government's law enforcement activities or to the success- ful criminal or civil prosecution of such individual or firm . If the Attorney General or his designee makes ...
Página 10
... individual or firm concerned . Nothing in this subparagraph ( b ) ( 1 ) shall prevent the reimposition of a suspension in accordance with subparagraph ( a ) , above , whenever such indictment , information or suit is returned or ...
... individual or firm concerned . Nothing in this subparagraph ( b ) ( 1 ) shall prevent the reimposition of a suspension in accordance with subparagraph ( a ) , above , whenever such indictment , information or suit is returned or ...
Página 11
... individual or firm from the con- tracts or subcontracts of a government department or agency or firm participating in any federally assisted construction work should be evidenced by a decision in writing , which decision sets forth ...
... individual or firm from the con- tracts or subcontracts of a government department or agency or firm participating in any federally assisted construction work should be evidenced by a decision in writing , which decision sets forth ...
Términos y frases comunes
administrative debarment adversary hearing Air Force American Bar Association applicable appropriate ARMED SERVICES PROCUREMENT ASPR Assistant Judge Advocate Assistant Secretary authorized award bids or proposals Buy American Act cause CINCPAC Committee Compliance Division Comptroller concerned contracting agencies contracting officer contractor or subcontractor contracts or subcontracts copy criminal conduct criminal or civil Davis-Bacon Act DCS/M debarred or ineligible decision Defense Supply Agency Department of Defense Department of Justice Department of Labor determination evidence executive agency fact Federal Airport Act federally assisted construction firm or individual fraud furnished government contracting Hq USAF individual or firm Joint Consolidated List liquidated damages ment Naval Material Navy NCEL notice of suspension performance persons or firms procedures Procuring Activity proposed debarment pursuant qualified reasonable Recommendation request responsible prospective contractor Secretary of Labor SERVICES PROCUREMENT REGULATION statutes Subpart supplier supra SUSPENDED BIDDERS Suspended Contractors tion Trial Examiner trial-type hearing violation
Pasajes populares
Página 43 - SEC. 3. (a) Every contract for the construction, alteration, or repair of any public building or public work in the United States...
Página 14 - In making the foregoing determinations the court shall review the whole record or such portions thereof as may be cited by any party, and due account shall be taken of the rule of prejudicial error.
Página 67 - Contracts for the construction, alteration, or repair of public buildings or public works In the United States or elsewhere...
Página 16 - Certain principles have remained relatively immutable in our jurisprudence. One of these is that where governmental action seriously injures an individual, and the reasonableness of the action depends on fact findings, the evidence used to prove the Government's case must be disclosed to the individual so that he has an opportunity to show that it is untrue.
Página 14 - Except as statutes otherwise provide, the proponent of a rule or order shall have the burden of proof.
Página 104 - B includes firms or individuals whom the Secretary of Labor has determined to be ineligible because they do not qualify as "manufacturers
Página 128 - The failure or refusal of a witness to appear at any such hearing or to answer any question which has been ruled to be proper shall be ground for the action provided in section 5 of the Walsh-Healey Public Contracts Act of June 30, 1936 (sec.
Página 113 - Whenever any contract includes a provision for liquidated damages for delay, the Comptroller General, on the recommendation of the head of the agency concerned, is authorized and empowered, by law, to remit the whole or any part of such damages as in his discretion may be just and equitable.
Página 127 - In any such proceeding the rules of evidence prevailing in courts of law or equity shall not be controlling.
Página 69 - ... the record of facts obtained by the original debarring agency, or upon a combination of additional facts with the record of facts of the original debarring agency.