Federal Securities Laws and Defense Contracting: Hearings Before the Subcommittee on Oversight and Investigations of the Committee on Energy and Commerce, House of Representatives, Ninety-ninth Congress, First Session, on ...U.S. Government Printing Office, 1986 |
Dentro del libro
Resultados 1-5 de 54
Página 18
... . During that time , estimates of the costs to complete the boats were frequently under revision , concurrently with the definition of the tasks required to be carried out . 1 It should be noted that in the June 1978 settlement 18.
... . During that time , estimates of the costs to complete the boats were frequently under revision , concurrently with the definition of the tasks required to be carried out . 1 It should be noted that in the June 1978 settlement 18.
Página 19
... complete the then contract would exceed the contract price by $ 843 million . The company accepted the Navy's negotiation position of $ 125 million in payment for the company's claims , which left a remainder of $ 718 million . Then the ...
... complete the then contract would exceed the contract price by $ 843 million . The company accepted the Navy's negotiation position of $ 125 million in payment for the company's claims , which left a remainder of $ 718 million . Then the ...
Página 21
... complete the 18 SSN 688 submarines and that he had called members of the Corporate Office management to tell them that Veliotis ' estimate of a $ 90 million overrun of the 1978 settlement figure was far too optimistic . I was further ...
... complete the 18 SSN 688 submarines and that he had called members of the Corporate Office management to tell them that Veliotis ' estimate of a $ 90 million overrun of the 1978 settlement figure was far too optimistic . I was further ...
Página 22
... complete estimates . I was more concerned about the Ashton efforts to undermine the validity of our insurance claims , which were our principal bargaining chips in negotiating a settlement of our outstanding differences with the Navy ...
... complete estimates . I was more concerned about the Ashton efforts to undermine the validity of our insurance claims , which were our principal bargaining chips in negotiating a settlement of our outstanding differences with the Navy ...
Página 28
... own estimate of the Ohio delivery date . Perhaps a complete tape of their conversation , plus the conversations of the previous day , would make that clear . In conclusion , we remain convinced that it was incumbent 28.
... own estimate of the Ohio delivery date . Perhaps a complete tape of their conversation , plus the conversations of the previous day , would make that clear . In conclusion , we remain convinced that it was incumbent 28.
Otras ediciones - Ver todas
Términos y frases comunes
Admiral Rickover Agreement Arthur Andersen ASHTON asked audit believe BILIRAKIS bill bribery BRYANT business conferences Buyeon Carabao Chair Chairman charges claim clearance committee Consultant contractor corporate aircraft cost counsel DCAA Department of Defense DINGELL disclosure discussion documents Duesenberg Dynamics Corporation DYNAMICS Electric Boat DYNAMICS PRIVATE INFORMATION ECKART Electric Boat Division employees Executive expenses Federal flights gentleman GERRY SIKORSKI gifts going Grand Jury gratuities issue Jenner John Lehman Lester Crown letter LEWIS Louis MACDONALD matter meeting memorandum ment million Navy negotiations overhead Oversight and Investigations paid party passengers payments Pedace person Pierre Laclede prior problem question record reimbursement request response Sawyer schedule Secretary SHELBY SIKORSKI SLATTERY statement Subcommittee on Oversight Subcommittee staff submarine submitted talking tape taxpayers tion told Trident trip Veliotis violation vouchers Washington WYDEN
Pasajes populares
Página 2 - In the councils of government, we must guard against the acquisition of unwarranted influence, whether sought or unsought, by the military-industrial complex. The potential for the disastrous rise of misplaced power exists and will persist.
Página 2 - ... Government, we must guard against the acquisition of unwarranted influence, whether sought or unsought, by the militaryindustrial complex. The potential for the disastrous rise of misplaced power exists and will persist "We must never let the weight of this combination endanger our liberties or democratic processes. We should take nothing for granted. Only an alert and knowledgeable citizenry can compel the proper meshing of the huge industrial and military machinery of defense with our peaceful...
Página 508 - Whether the cost is of a type generally recognized as ordinary and necessary for the conduct of the...
Página 253 - Contractor, to any officer or employee of the Government with a view toward securing a contract or securing favorable treatment with respect to the awarding or amending, or the making of any determinations with respect to the performing of such contract...
Página 544 - Judgment upon the award rendered may be entered in any Court having jurisdiction or application may be made to such Court for a judicial acceptance of the award and an order of enforcement, as the case may be.
Página 284 - Memorandum for Secretaries of the Military Departments, Chairman of the Joint Chiefs of Staff, Under Secretaries of Defense Director, Defense Research and Engineering, Assistant Secretaries of Defense, General Counsel of the Department of Defense.
Página 509 - ... the relative benefits received or other equitable relationship. Subject to the foregoing, a cost is allocable to a Government contract If it...
Página 532 - Terms with respect to which the confirmatory memoranda of the parties agree or which are otherwise set forth in a writing intended by the parties as a final expression of their agreement with respect to such terms as are included therein may not be contradicted by evidence of any prior agreement or of a contemporaneous oral agreement...
Página 427 - Thank you, Mr. Chairman. Mr. DINGELL. The time of the gentleman has expired. The Chair recognizes now the gentleman from New York, Mr.
Página 509 - ... in accordance with the relative benefits received or other equitable relationship, subject to the foregoing, a cost is allocable...